So, we’d finally got the utility room into a useable state, laid the base for the extension, and we’ve sorted out the awful hallway. So it was probably time for the actually extension to be done. And in February 2024, builders came to the house and started turning the garden in to our very own builders merchant, with the builders very own shed. And, most importantly, we gave them their own tea making station, with biscuits, so they could eat and drink as much as they liked.






The plan here was to do to all of the external works, and get it all sealed up, before knocking through the old external walls to connect the old and the new parts together. This part was kind of okay, because we still had access to all of the original parts of the house, like the kitchen, and I was still able to set up my ‘work from home’ station, although it was a bit noisy being right next to all of the work.




Just another brick…
Because of the classic British weather, the first few month of 2024 turned out to be very wet. With hindsight, we now know that this was pretty normal for the southwest, in winter, when the global climate is in breakdown. But it did slow this whole section down, and pushed everything back by a good few weeks. I remember builders going on to the local news and saying how they hadn’t been able to do any building works because the weather had been so bad, and if it didn’t change soon, they would start getting into financial hardship. So I was grateful that our builders had managed to get anything done at all.
And slowly but surely, the walls did go up. And even the Building Inspector was impressed with the workmanship, so we were feeling good about the progress.




And as the walls grew, and February turned into March, it was time for some scaffolding to go up as well, and the steel beams to be added in.




I would be lying if I said the scaffolding wasn’t my favourite bit, cos I really enjoyed going up on the scaffolding and taking in the views (when the weather was decent).




The weather was still pretty awful most of the time, and so the back garden was getting muddy and difficult to traverse. But the builders kept at it and more bits came together. Whenever there was a good weather day, I would try and pop out and get some shots.






Levelling Up
Thankfully spring was getting closer, although winter was refusing to let go. But we got up to the second level, and it was amazing how fast it felt like things were going. We could see the shape of the extension all coming together, so there couldn’t be much longer left, right?






…maybe not.
But we had reached the roof already. And as we were now into April, we had some blue skies, so it’s the perfect time to take off some roof tiles and put the new roof on…except the weather had other ideas and despite the builders best efforts to keep everything watertight, we did get a bit of a deluge that came in and flooded one of our bedrooms.

Thankfully it was one of the rooms that we hadn’t decorated since moving in (yes, we still have one) so it could have been a lot worse. Thankfully the rain stopped before we had to got to bed, and we didn’t have to spend all night emptying tubs of rain water.
And after that, the builder pressed on to get it watertight again, and get the roof finished.






Thankfully, that was the last winter storm we really had, which meant that we didn’t have to worry about any more delays (caused by the weather, at least).






This view reminds me that we really need to get on and put some velux windows installed in the attic so that we can enjoy that view again.

The end of one journey
And so, the next crucial step was finishing off the rooves, getting the tiles on, and the velux window in, so that we could have something that looked like a proper extension. And by mid-April, we were there.







There was no rush, but because the weather had finally stopped being miserable, we were even able get the windows in too.




Technically, by this point, the builders had already started some of the internal works, and you can read about that in part 2.