Yet another job that was unfinished from the extension, was the pantry (or larder, depending on where you’re from). Part of the old kitchen was now between 2 doors, that were close by. It was a bit of an awkward space, but we figured out early on that it would be really handy to use it as a pantry, to give us additional room to store jars and cans, and even some of the bulkier items that just don’t go anywhere else.

Currently it was just used like a cupboard, so just contained a few bulky items. What we wanted was something that could house a lot of our tins and cans, and all of the nice things we’d made in previous years, like jars of jams and marmalades, and bottles of booze. By shear luck, we managed to find a couple of photos of a similar project someone else had done, that was exactly the kind of thing we were looking to do, in an almost identical space. This made it much easier to understand what we needed to do!

The project got off to a rather slow start. We put this on our list of jobs to do in 2026, with a plan to do it at the start of the year, when we had plenty of spare time to get it done. I worked out some designs, took it to a timber merchant and even got a quote, and was about to pay for it…but mother nature had other ideas (see our Storm Chandra update).

So that meant we needed to wait while we sorted out all of that.

7 Months Later…

Eventually, once we’d sorted out the leak, the mould, and the repainting, the pantry was in a position to be worked on again. We went back to the timber merchant and paid the invoice. During that whole time, the plans I drew up were stuck to the fridge, so we got to look at them everyday, but that was all.

Until we finally got a message to say that the wood was ready to be collected, and we had a week off from work, where we could actually do it.

Something of a theme in these updates is my awful measuring and planning skills. I’ve managed to incorrectly measure and calculate floor tiles, and the amount of fence paint we’d need. And so it shouldn’t be surprising that I managed to get the wood order wrong too!

Mistake #1: I managed to get the length of one of the shelves wrong. And this was because at the last minute, I changed the depth of the back shelves by 100mm but forgot to shrink the side shelves by the same amount. And I got the length of the wall batons wrong, as I didn’t take into consideration the overlap in the corners.
These mistakes weren’t so bad, as they could be fixed by cutting the wood down. Unfortunately we didn’t have the tools for that, so we had to take a late night drive down to Plymouth to borrow a mitre saw, so that we could get started the next day and start cutting things down.
And because the wood we used was quite hard, we did try to buy a nice new saw blade, so that we could get a nice clean edge on it, but despite trying for an hour to get the new blade to fit on the saw, it just didn’t want to know, so we gave up on that!

Mistake #2: For some reason I’d not requested enough batons for a couple of the shelves. I have no idea why I did this. It was a simple case of having 4 shelves and so needing 4 batons, but I only asked for 2. No reason to do that, but I did. By sheer luck, the timber merchant gave us a couple of left over cuts, that were close in width (but not exactly the same) as what we needed. So we used the mitre saw to create a couple of make-shift batons.

Mistake #3: I ordered too few brackets. Not sure why. I probably just counted them wrong.

What’s frustrating is that I could have used that 7 month gap to do a check on all of the measurements and my counts. Coming back after all that time would have meant I had a fresh pair of eyes and could have spotted my mistakes, but I didn’t. I was far too focussed on getting the wood in time for our week off, so we could get it done. More haste, less speed.

When Life Gives You Labels

Encouraged to not make any more mistakes, and seeing how many pieces we had, I could immediately see an error trap where it was going to be very easy to mix up some of the pieces, and if I cut the wrong notch out of the wrong piece, or measure a piece in one location, but then use it in another, then there would be a good chance of it not all fitting together, and might even mean we’d need to reorder some of the pieces. Since it was already expensive wood, I was keen to lot let this happen. So I started the project by making a number of labels for each piece, so I could distinguish between each one, and the label also helped me to remember which way each pieces should be orientated.

This probably was the most useful thing that I did. It saved me so much time over the week, and meant I didn’t have to keep double-checking everything. And it was much easier to be able to ask for a specific piece by name when we were working together.

So after using the first day to collect the wood and the right tools, we used the second day to get the wood ready. This did take a while, but I was trying to be accurate and not rush through it and make more mistakes.
This day also coincided with the landscaper coming and doing a bit of work in the garden, which was lucky as he apparently had the same mitre saw as the one we borrowed, and so knew how to work it, which I did not.

At the same time, we thought it would probably be a good idea to apply some kind of varnish to the shelves. Despite buying particularly hard-wearing wood, we knew they were going to take a bit of a beating over the years, and maybe even the odd spill, so some sort of extra protection, might be a good idea.
We’d use Osmo Oil before, and still had some left over, so we used that. The only annoying thing was that each piece then needed 24Hrs to dry. Lucky the rest of the project was going pretty slow, so this wasn’t a problem.

So once I knew what I needed to do, I got all of the pieces ready, and by day 3, we got the batons on the wall.

Frickin’ Laser Beams

Putting up shelving was also the perfect opportunity to use a new laser level that I recently purchased that made it easy to mark up levels lines the whole way around the pantry. Unfortunately I didn’t have the best tools for cutting out the notches in the shelves, so some of those were a bit uneven, and messy.

But with a little bit of luck, we managed to get all of the shelves to fit together.

One important thing for me was the ability to fit 2 cans on top of each other on the shelves. It wasn’t essential, but when I worked out the plan, I was kind of limited by the space that was available. The slope at the back meant I couldn’t go any higher, and there was some trunking in the middle which we had to work around as well. This meant we had a specific gap to work with, and a if we put in 2 shelves in-between, each should be just big enough to allow for 2 tins to be stacked. But it was close.
I didn’t want to end up with a shelves that were slightly too small, because it would be a waste of space. So I was glad when we tested it and found that 2 would fit. Although I didn’t take into account the extra few millimetres on the brackets, so they 2 won’t fit everywhere.

On the forth day, I was able to get all of the brackets on (that we had), removed all of the stickers, screwed in the shelves to the batons, and then cleaned up all the mess, so we could finally start putting some items on the shelves and using the pantry as we’d originally planned.