Phase 2: Can the Real Extension Please Stand Up? (part 1)

So, we’d finally got the utility room into a useable state, laid the base for the extension, and we’ve sorted out the awful hallway. So it was probably time for the actually extension to be done. And in February 2024, builders came to the house and started turning the garden in to our very own builders merchant, with the builders very own shed. And, most importantly, we gave them their own tea making station, with biscuits, so they could eat and drink as much as they liked.

The plan here was to do to all of the external works, and get it all sealed up, before knocking through the old external walls to connect the old and the new parts together. This part was kind of okay, because we still had access to all of the original parts of the house, like the kitchen, and I was still able to set up my ‘work from home’ station, although it was a bit noisy being right next to all of the work.

Just another brick…

Because of the classic British weather, the first few month of 2024 turned out to be very wet. With hindsight, we now know that this was pretty normal for the southwest, in winter, when the global climate is in breakdown. But it did slow this whole section down, and pushed everything back by a good few weeks. I remember builders going on to the local news and saying how they hadn’t been able to do any building works because the weather had been so bad, and if it didn’t change soon, they would start getting into financial hardship. So I was grateful that our builders had managed to get anything done at all.

And slowly but surely, the walls did go up. And even the Building Inspector was impressed with the workmanship, so we were feeling good about the progress.

And as the walls grew, and February turned into March, it was time for some scaffolding to go up as well, and the steel beams to be added in.

I would be lying if I said the scaffolding wasn’t my favourite bit, cos I really enjoyed going up on the scaffolding and taking in the views (when the weather was decent).

The weather was still pretty awful most of the time, and so the back garden was getting muddy and difficult to traverse. But the builders kept at it and more bits came together. Whenever there was a good weather day, I would try and pop out and get some shots.

Levelling Up

Thankfully spring was getting closer, although winter was refusing to let go. But we got up to the second level, and it was amazing how fast it felt like things were going. We could see the shape of the extension all coming together, so there couldn’t be much longer left, right?

…maybe not.

But we had reached the roof already. And as we were now into April, we had some blue skies, so it’s the perfect time to take off some roof tiles and put the new roof on…except the weather had other ideas and despite the builders best efforts to keep everything watertight, we did get a bit of a deluge that came in and flooded one of our bedrooms.

Thankfully it was one of the rooms that we hadn’t decorated since moving in (yes, we still have one) so it could have been a lot worse. Thankfully the rain stopped before we had to got to bed, and we didn’t have to spend all night emptying tubs of rain water.
And after that, the builder pressed on to get it watertight again, and get the roof finished.

Thankfully, that was the last winter storm we really had, which meant that we didn’t have to worry about any more delays (caused by the weather, at least).

This view reminds me that we really need to get on and put some velux windows installed in the attic so that we can enjoy that view again.

The end of one journey

And so, the next crucial step was finishing off the rooves, getting the tiles on, and the velux window in, so that we could have something that looked like a proper extension. And by mid-April, we were there.

There was no rush, but because the weather had finally stopped being miserable, we were even able get the windows in too.

Technically, by this point, the builders had already started some of the internal works, and you can read about that in part 2.

Phase I: Mould Begone (part i)

It’s been more than four years since any updates from us, but to be fair , that was 2019, and some rather big things happened after then, which put the breaks on a lot of people plans! But we’ve also been bad and not kept you all up-to-date with the things that have been going on. So here is a catch up!

During this time, we’ve had three new jobs between us, increased our Lego collection way too much, and been trying to get fit and lose some weight. All in between Zoom calls, episodes of Tiger King, and trying to dodge coronavirus. So to sum it up, we’ve not been very busy with any DIY for the last three years!

But it’s not been a complete waste, because in 2021 we decided to finally move ahead in some of our plans for the extension.

Whilst our funds were pretty close the the amounts we’d been quoted in the past, we’d seen enough epidoses of Grand Designs (and Homes under the Hammer), to know that in almost every case the costs and timescales always end up way more than originally expected. So we didn’t want to try and do it all and run out of money before the end.

But during one of the visits from a builder, it was mentioned about having the utility room stripped out, insulated and redecorated as part of the extension plans in order to get rid of the black mould, and make it all good. The builder gave us 2 quotes for both the new part of the extension, and the improvements to the utility room, and it was this that gave us the idea about splitting the works needed into the 2 parts that needed doing.

Over the previous six years of living in the house, the black mould in the utility room had crept further and further up the walls and bloomed in previously untouched areas. And when it rained heavily, the water would seep in around the door frame and though the holes in the roof, despite having had the roof professionally repaired a few years ago.

So we really wanted to try and sort this out once and for all, and we spoke with the architect to see if it could be done. Fortunately it could be, without having to change things very much.

The drains in the garden would need to be moved, which is something that we would need to do as part of the extension foundations anyway, so we decided to include the foundations as part of the work in this phase. And since we were doing the utility at a different time to the bathroom, we decided to add a shower into the utility as well. It’s something that we previously thought about doing, and we thought it would come in handy when the bathroom works will take place, and we won’t have a bath/shower.

This had the added benefit of being enough work for the council to accept the plan as being officially started, which meant that our planning permission wouldn’t expire, as well as having a new (mould free) utility room without having to pay the huge cost of both phases at once (which would have required a few more years of saving)!

There was another issue that splitting the work into phases also helped with, and that was inflation! This was in mid-2021, and so the world was beginning to open up again, and building supplies were struggling to keep up with demand, so the price of a lot of materials were increasing month after month. That meant that a quote given to us at this point might be considerably out of line with the final price we’d end up paying. So at least by only doing a part of all of the works, we’d be able to stop the possibility of inflation becoming a bigger problem for us (which as it turned out, was a very good thing).

We went through the normal (long) processes, with getting quotes from a few different builders and eventually works started in November 2021, and were due to finish around Christmas (although actually ended up finishing in April 2022, but we knew it would always take longer).

First jobs first – Out with the old

Before any works could begin, we had to try and clear out as much of the stuff in the utility as we could move, which was a lot more than we’d realised.

It’s amazing to see how much things have changed, now that we’re looking back.

Second Job – Foundations

Obviously starting in November meant that the builders were already going to have to face into a lovely English winter and its weather, but it was relatively mild, although I am still glad it wasn’t us out there every day in the mud.

One thing that the builders did request of us, was the need to knock down part of the back wall, to give access to some machinery to dig up the ground. By sheer luck, the wall in the back garden backs on to a road, that would allow the access, and we discovered that the wall acutally belonged to us too! And we think we happen to be the only house along our neighbours who happen to have our back garden back on to another road, so for the first time, it actually felt like we had a bit of good luck!

The machinery defineitly helped with the groundworks, and made quick work of it, even if it did effectively turned out garden into somehting that looked like it could be used in a WWI film set!

And becaue we now both work from home, we were actually around for almost all of the works, which meant that we were able to have a little play around with some time-lapse videos.

And eventually things started to come together, with soak-aways being added, and foundations being laid.

Even the new drains came together well, although I know it took many days of being sat in the rain to finish it off.

It felt pretty strange to actually see the foundations going in, when we’d spent so long talking about it.

And although we tried our very best, the nice smooth concrete surface did end up with a few cat paw prints in it!

The garden was left in ruins, but you can’t have everything!

See part 2 for the details on the Utility room!

It’s been a while…

After nearly a year without an update (the reason for which we will come on to), I thought now would be a good time. It’s approaching summer and we have been working in the garden, and although not much has changed in the house, our application for planning permission has been submitted to the council.

We have gone with our original idea of having a ‘one and two story’ extension, this expands the upstairs bathroom, the kitchen and the dining room.  We now just have our fingers crossed that permission is granted.

So with that in mind, we are trying to save as much money as possible, and we have mainly been making a few improvements to our front garden.

IMG_2820

Pictured above: Our established ‘Loddon Blue’ Lavender and ‘Totally Tangerine’ Geums

On the last May bank holiday weekend, Paul and I went and bought nine different types of lavender to plant in the front garden. These now line the wall that runs parallel to our house. We’ve left space for them to grow so they do look a bit meek at the moment, but we’re looking forward to having a long row of fragrant shrubbery in years to come.

IMG_2814

We have quite solid clay soil which makes digging more than a couple of inches very difficult. Coupled with the buried bricks, making space for the lavender was not as easy as we’d hoped.

Above: The variety of lavender now planted in the garden. 

The two french lavenders ‘Tiara’ and ‘Regal Splendour’ didn’t come with tags, as we had to go to an entirely different garden centre to find these. I intend to document the order in which they have been planted in a garden book so we don’t forget.

IMG_2850

Earlier on in the year, in March we re-planted our hanging basket with a variety of succulents and an alpine lavender plant. The reason we went for those is because last year the plants tended to dry out very quickly and didn’t do well. It’s all doing much better and needs a lot less watering than last year’s arrangement.

IMG_2847

We also replaced a the couple of plants that didn’t make it through the winter in our strawberry planter, it’s now bursting at the seams. Again, alpines and succulents seem to be the way forward for some easy gardening.

IMG_2846

Above: The bees have been loving the abundance of chive flowers this year.

Our kitchen garden is doing well. We’ve removed most of the mint and had to re-plant it in spots where we don’t mind it taking over (on the ground below the raised bed). It’s now happily mingled with escaped strawberries, sweet woodruff and chamomile (and a few determined weeds). And we replaced a few of the things we lost over the years like sage and lemon verbena (which didn’t survive the Beast from the East last year).

We have also pulled out and replaced some of the plants near the top of the front garden.  I have tried to introduce some more colour as it was previously just a bland blanket of green.

IMG_2853

From left: Hart’s Tongue Fern, Carex ‘Bronze Form’, Berberis ‘Thunbergii Orange Rocket’, a hosta (whose tag we lost), Heuchera ‘Marmalade’ & Tiarella ‘Spring Symphony’

We’re hoping it will all fill out a little bit and look even better next year, providing the slugs don’t eat them.

The plan is to begin work on our extension in 2020. The application was submitted to the local council by our architect in April and the decision was meant to be made on 6 June. We have yet to hear anything, but are hoping for some good news soon so we can start making some more concrete plans!