Wild Wild West

2026 started off with a low note. We had a beautiful New Year’s Day, followed by several weeks of non-stop rain, including a few named storms. And one of those storms, called Chandra, hit on the 26th Jan.
And after seeing rain constantly all day and all night, we woke up to find some damp patches on one of the walls, so apparently there was a leak somewhere.

The patches were a bit random, so we couldn’t be sure where that leak was coming from. There was nothing obvious outside, like any missing roof tiles, but there was plenty of evidence of how extreme the weather had been. And the attic did show evidence that the leak may have been going on for a while.

And more importantly, the leak also found it’s way down to the newly built pantry. The timing was actually pretty lousy (or lucky, depending on your philosophical outlook) because we had just been to the local carpenter, in readiness to order some wood to build our pantry shelving. And the day before this happened, I’d received the confirmation email, with a link to pay for it. So obviously that particular job had to take a short break until later in the year.

Eventually the constant downpours did subside and the patches stopped expanding, and even dried out. What was left were patches of peeling paint and stained paint.
We decided it was best to give these some time to really dry out before looking to fix the patches, but in the meantime we’d contact some roofers to see if they can come out and figure out what’s wrong. Unfortunately, following a very storming few months, roofers were in high demand, so even trying to get hold of one turned out to be a tall ask. After a few weeks we hadn’t heard back from anyone.
Luckily for us, our neighbours directly opposite, were having some work done to a small bit of roofing, and so I contacted the number on their van to see if they were able to come and have a look while they were in the area. And they thankfully obliged.

Mind the Gap

The roofer popped over (after he’d finished his actual job) and pulled out an extremely long ladder, so he could get up and have a look for any damage. As expected, there wasn’t anything significant, but there were a log of small gaps in the old mortar, that rain could easily makes it’s way into. Especially if that rain was constant for a long period of time.

Fortunately that also meant that for just a few hundred quid, he could come and fill in those gaps, waterproof the area, and add a cowl, to minimise any future of water ingress. And after a few weeks, the scaffolding was erected, and then a few weeks after that they came and did the repairs.

This was also at the same time the landscapers started working on the back garden, and the same time as discovering that there was a problem with the new kitchen drains.

Ignoring those other job, all we needed to do now, was to sort out the peeling paint inside.

Climate Breakdown to the Rescue

We had to be sure that everything was dried out before we could try and repair anything at all, so we were hoping that once spring was out of the way, we’d get a nice spell of warm and dry weather to make sure everything was back to normal.
And the weather delivered! Summer 2026 turned out to be the hottest on record. So after the 5th heatwave, and experiencing twenty one consecutive days of maximum temperatures 25°C and higher, the house had been properly baked in the summer sun, and we thought it was probably a good time to finally repair the paint.

We also decided that if we were going to have to repaint the hallway and stairs, that we might also go for a new colour too. We originally just did a pure brilliant white, to make things easy. But first we needed to scrape of the paint that was flaking and peeling.

This didn’t seem too bad, but it was one of those jobs where you start peeling and suddenly a lot more comes off than you were expecting, and then as you try and make sure you’ve got every loose bit, the scraper gets another part and peels off yet more.
Undeterred by this, we were keen to get every last bit of loose paint off. And we then treated it with some Zinsser Peel Stop, to try and make sure there was no chance of any more coming off.

It did technically work, but as we went over a couple of patches with the new paint and a roller, it did manage to lift some more flakes off. But these were all areas that we hadn’t scraped beforehand, so the Peel Stop did it’s job, these were areas we hadn’t been treated, because we couldn’t see that they were there. So a second round of scraping, treating, and painting, did the trick.

And luckily the new paint even managed to make the walls look a bit more smooth and even too, so we’re happy with. Let’s see what Winter 26/27 has in store for us.

Phase I: Mould Begone (part i)

It’s been more than four years since any updates from us, but to be fair , that was 2019, and some rather big things happened after then, which put the breaks on a lot of people plans! But we’ve also been bad and not kept you all up-to-date with the things that have been going on. So here is a catch up!

During this time, we’ve had three new jobs between us, increased our Lego collection way too much, and been trying to get fit and lose some weight. All in between Zoom calls, episodes of Tiger King, and trying to dodge coronavirus. So to sum it up, we’ve not been very busy with any DIY for the last three years!

But it’s not been a complete waste, because in 2021 we decided to finally move ahead in some of our plans for the extension.

Whilst our funds were pretty close the the amounts we’d been quoted in the past, we’d seen enough epidoses of Grand Designs (and Homes under the Hammer), to know that in almost every case the costs and timescales always end up way more than originally expected. So we didn’t want to try and do it all and run out of money before the end.

But during one of the visits from a builder, it was mentioned about having the utility room stripped out, insulated and redecorated as part of the extension plans in order to get rid of the black mould, and make it all good. The builder gave us 2 quotes for both the new part of the extension, and the improvements to the utility room, and it was this that gave us the idea about splitting the works needed into the 2 parts that needed doing.

Over the previous six years of living in the house, the black mould in the utility room had crept further and further up the walls and bloomed in previously untouched areas. And when it rained heavily, the water would seep in around the door frame and though the holes in the roof, despite having had the roof professionally repaired a few years ago.

So we really wanted to try and sort this out once and for all, and we spoke with the architect to see if it could be done. Fortunately it could be, without having to change things very much.

The drains in the garden would need to be moved, which is something that we would need to do as part of the extension foundations anyway, so we decided to include the foundations as part of the work in this phase. And since we were doing the utility at a different time to the bathroom, we decided to add a shower into the utility as well. It’s something that we previously thought about doing, and we thought it would come in handy when the bathroom works will take place, and we won’t have a bath/shower.

This had the added benefit of being enough work for the council to accept the plan as being officially started, which meant that our planning permission wouldn’t expire, as well as having a new (mould free) utility room without having to pay the huge cost of both phases at once (which would have required a few more years of saving)!

There was another issue that splitting the work into phases also helped with, and that was inflation! This was in mid-2021, and so the world was beginning to open up again, and building supplies were struggling to keep up with demand, so the price of a lot of materials were increasing month after month. That meant that a quote given to us at this point might be considerably out of line with the final price we’d end up paying. So at least by only doing a part of all of the works, we’d be able to stop the possibility of inflation becoming a bigger problem for us (which as it turned out, was a very good thing).

We went through the normal (long) processes, with getting quotes from a few different builders and eventually works started in November 2021, and were due to finish around Christmas (although actually ended up finishing in April 2022, but we knew it would always take longer).

First jobs first – Out with the old

Before any works could begin, we had to try and clear out as much of the stuff in the utility as we could move, which was a lot more than we’d realised.

It’s amazing to see how much things have changed, now that we’re looking back.

Second Job – Foundations

Obviously starting in November meant that the builders were already going to have to face into a lovely English winter and its weather, but it was relatively mild, although I am still glad it wasn’t us out there every day in the mud.

One thing that the builders did request of us, was the need to knock down part of the back wall, to give access to some machinery to dig up the ground. By sheer luck, the wall in the back garden backs on to a road, that would allow the access, and we discovered that the wall acutally belonged to us too! And we think we happen to be the only house along our neighbours who happen to have our back garden back on to another road, so for the first time, it actually felt like we had a bit of good luck!

The machinery defineitly helped with the groundworks, and made quick work of it, even if it did effectively turned out garden into somehting that looked like it could be used in a WWI film set!

And becaue we now both work from home, we were actually around for almost all of the works, which meant that we were able to have a little play around with some time-lapse videos.

And eventually things started to come together, with soak-aways being added, and foundations being laid.

Even the new drains came together well, although I know it took many days of being sat in the rain to finish it off.

It felt pretty strange to actually see the foundations going in, when we’d spent so long talking about it.

And although we tried our very best, the nice smooth concrete surface did end up with a few cat paw prints in it!

The garden was left in ruins, but you can’t have everything!

See part 2 for the details on the Utility room!